We are pleased to be able to provide a Construction Update at The Grange, Waurn Ponds.
Since commencing construction in November 2022, the contractor has been progressing well through challenging weather conditions.
The current status of works are:
- The entrance boulevard & Banrock Court are taking shape, with curb install underway.
- Concrete sleeper retaining walls are almost completed
- Feature stone retaining walls will commence construction shortly.
- Hams Road widening works will be completed by the start of June.
Several purchaser groups were fortunate to take a walk down Banrock Court to catch a glimpse of the outlook from their purchased lot.
Anticipated Settlement Date for all releases is still on track for Q3 2023.
We will keep you updated of further progress as civil construction continues.